Work Completed
• Replaced concrete sleepers in designated worksite (1 in 3)
• Regulated ballast
• Tamped worksite
• Brushed Worksite
• Changed rails throughout the worksite (30ft/60fts)
• Removed any scrap i.e. sleeper/smalls/spoil
Worked alongside NWR to ensure volumes quota was met in a safe manner during restricted possession times