Bond Street to Baker Street (Acid Ingress)

All Project Profiles

Project Description

Work Completed

  • Primary sealing of certain flange points
  • Extrados injection grouting of each tunnel ring
  • Final flange sealing where required
  • Mobilised and demobilised site
  • Provided and maintained inomat M8 pumps

All work was completed in the allotted 4hr window each night until the brief was achieved.

The resources used by SES were all trained in PWTEH, fitters, electricians, TOO2/3 hand back, lift and escalator, track trolley, PASMA.

Sealing of one section of the tunnel was proving difficult due to the large voids behind the tunnel segments

SES were tasked in finding a way of injecting sand through the 32mm grout hole.

There was no portable machine on the market capable of achieving this doing this so SES in conjunction with APP designed and developed a portable pressurised tank that could be used for injecting sand behind the lining.

The machine was built and tested and transported into the tunnel where it was used with success.


Client

London Underground

Brief

Prevent the ingress of acid water of 188 rings


chevron-down