Work Completed
- Replaced existing tunnel lining sections (EPC) with Spheroidal Graphite Iron rings (SGI)
- Each ring comprised of 13 sections (EPC) to be removed and replaced by 5 new rings (SGI)
- Operated and maintained SHP
- Utilised a number of 27 and 52 hour possessions
All work was completed in the allotted 4hr window each night until the brief was achieved by:
- Operational Crew
- Machine Fitters/Electricians
- Handback Engineers
- Maintenance Crew
SHP
To familiarise themselves with how to operate and maintain the plant, SES operators spent time;
- In the factory at Milton Keynes where the plant was manufactured
- At a disused siding to carry out trials to develop a safe system of work