Bond Street to Baker Street Tunnel Relining

All Project Profiles

Project Description

Work Completed

  • Replaced existing tunnel lining sections (EPC) with Spheroidal Graphite Iron rings (SGI)
  • Each ring comprised of 13 sections (EPC) to be removed and replaced by 5 new rings (SGI)
  • Operated and maintained SHP
  • Utilised a number of 27 and 52 hour possessions

All work was completed in the allotted 4hr window each night until the brief was achieved by:

  • Operational Crew
  • Machine Fitters/Electricians
  • Handback Engineers
  • Maintenance Crew

SHP

To familiarise themselves with how to operate and maintain the plant, SES operators spent time;

  • In the factory at Milton Keynes where the plant was manufactured
  • At a disused siding to carry out trials to develop a safe system of work

Client

Bond Street to Baker Street Tunnel Relining

Brief

Reline 358 rings (215m of tunnel) using 2 bespoke Segment Handling Plant (SHP)