Inverkeithing Switch Installation

All Project Profiles

Project Description

Work Completed

•Two RRVs (Liebherr A924s) carried out a tandem lift to remove the existing switch and transport it away from the worksite.

•Two RRVs then performed a tandem lift to install the new switch.

•Closure rails were installed within the worksite.

•RRVs supported NWR with snagging activities.

Due to restricted access, NWR implemented traffic management to ensure timely delivery of RRVs, attachments, and trailers.


Client

Network Rail (NWR)

Brief

Switch installation


chevron-down