Work Completed
The works were planned over a two-year programme and were successfully delivered without any overruns. The team consistently achieved high productivity levels, installing approximately 10 m³ of slab track per shift
Operations were carried out during extended engineering hours Monday-Wednesday, requiring careful planning, sequencing, and coordination to maximise output within limited possession windows
Operate and maintain Volumetric Concrete Mixer (VCM) train to support slab track system installation within the live underground railway in compliance with LUL standards and procedures