Work Completed
- Two RRVs (Liebherr A924s) carried out a tandem lift to remove the existing switch and transport it away from the worksite.
- Two RRVs then performed a tandem lift to install the new switch.
- Closure rails were installed within the worksite.
- RRVs supported NWR with snagging activities.
Due to restricted access, NWR implemented traffic management to ensure timely delivery of RRVs, attachments, and trailers.