Work Completed
- Carried out dig, removed spoil including rail and sleepers and loaded into engineering train.
- Unloaded ballast from train.
- Worked with NWR to ensure ballast levels are correct.
- Unloaded new sleepers from train and placed at the worksite (650mm spacing).
- Installed new rail.
- Dropped and tamped ballast which will gain access at Hillside RRAP.
Multiple OTP onsite - CC/MCs maintained appropriate exclusion zones.
Worked alongside multiple personnel from different companies to achieve results.