Kinnaber Disruptive Works

All Project Profiles

Project Description

Work Completed

  • Carried out dig, removed spoil including rail and sleepers and loaded into engineering train.
  • Unloaded ballast from train.
  • Worked with NWR to ensure ballast levels are correct.
  • Unloaded new sleepers from train and placed at the worksite (650mm spacing).
  • Installed new rail.
  • Dropped and tamped ballast which will gain access at Hillside RRAP.

Multiple OTP onsite - CC/MCs maintained appropriate exclusion zones.

Worked alongside multiple personnel from different companies to achieve results.


Client

Network Rail (NWR)

Brief

Kinnaber Disruptive Works